Big Apple Striping, Inc. is scheduled to begin painting and striping of the campus on Friday, Aug. 1, 2014, weather permitting. The tentative schedule will begin with the gravel parking areas and Parking Lot #3, and should take approximately two days to complete.
Additional striping will be completed as follows during the week of Monday, Aug. 4 through Friday, August 8, 2014:
1. Speed bumps around Loop Road and at guard booths at the main entrance and east entrance gate
2. Stop bars – various areas throughout campus
3. Crosswalks on the Administrative Loop, main entrance, and east of Building 1S on the Loop Road
4. Dolphin Cove disabled spaces
If you have any questions or concerns please contact maryjeanne.hennessy@csi.cuny.edu.